Scope

  • FERMA performed the demolition of a two-story, 360,000-square-foot reinforced concrete parking garage at one of the busiest shopping malls in the world.

  • An emergency egress path was maintained throughout demolition, allowing the mall to remain fully operational without disrupting adjacent Bank of America and Chase Bank facilities.

  • The parking garage demolition was completed two weeks ahead of schedule while maintaining continuous public access and safety controls.

  • Following demolition, FERMA executed mass excavation of approximately 240,000 cubic yards of soil while the mall remained open during construction.

  • To maintain schedule, FERMA averaged approximately 60 double-bottom trucks moving 280 loads daily through an active commercial environment.

  • Excavation and hauling operations were optimized using a custom-built excavator equipped with a specialized bucket, enabling efficient loading and reduced congestion throughout the site.