Job Overview |
|||||||
Structure: | 1 Mile Elevated Rdway | ||||||
Bid Schedule: | 24 Hrs. | ||||||
Actual Schedule: | 24 Hrs. | ||||||
Injuries: | 0 | ||||||
Recycling |
|||||||
Job Totals (tons) | 67,600 | ||||||
Recycled: | 100.0% | ||||||
Scope |
|||||||
Demolish Approximately 1 mile of elevated bridge in 24 hours. Road was being rebuilt after us and re-opened 15 minutes early for Monday morning traffic. Over 60 machines were used in 7 different crews to meet production goals that were tracked every 15 minutes. Limited time and space were issues as well as sequencing of activities to preserve access. |
Doyle Drive
San Francisco, CA.