Job Overview |
||||||||
Structure: | 20000 SF | |||||||
Bid Schedule: | 8 Weeks | |||||||
Actual Schedule: | 5.2 weeks | |||||||
Injuries: | 0 | |||||||
Recycling |
||||||||
Job Totals (tons) | 38,145 | |||||||
Recycled: | 99.8% | |||||||
Scope |
||||||||
Demolish commercial building and dig for new 3 story underground parking garage. Job was downtown Palo Alto and required all concrete was processed and recycled on-site. This required constant communication with trucks since the site could only handle 2 at a time. Ferma moved over 2,000 loads of material while loading next to traffic a mere 3′ away. Job was completed two and a half weeks early and without incident. | ||||||||
Lytton
Palo Alto, CA.