Job Overview

Structure: 70000 SF
Bid Schedule: 35 days
Actual Schedule: 32 days
Injuries: 0

Recycling

Job Totals (tons) 16,200
Recycled: 99.8%

Scope

Demolished an elevated road over 150′ high dam. Machines were drained of their hydraulic fluid and replaced with peanut oil to protect the drinking water from a possible spill. Great emphasis was place on protecting any material from falling on either side of the dam, as well as over a frog habitat. FERMA built a temporary wood and steel deck over them to protect them during the demolition.